In accordance with Article 6 of the Law on Real Estate Business, THT Development Company Ltd. (THT Development) officially discloses the full legal information of Starlake The Prime – K8CT1, including the Land Use Rights Certificate, the Sales Permit for off-plan housing and the guarantee contracts with Shinhan Bank and BIDV.
Location
Land Plot K8-CT1, Central Area of Tay Ho Tay New Town, Xuan Dinh Ward, Hanoi
Site area
2.3 ha (23,168 m²)
Products
656 premium apartments
Progress
Foundation completed
As part of our commitment to transparency, THT Development discloses the project’s legal information as follows:
Part 1Real estate project information
01
Decision on Investment Policy
No. 501/QD-UBND dated Jan 25, 2021, amended by Decision No. 815/QD-UBND dated Feb 07, 2024.
02
Decision on Land Allocation
No. 6102/QD-UBND dated Nov 25, 2024, issued by the Hanoi People’s Committee.
03
Approved Detailed Planning
Decision No. 5581/QD-UBND dated Sep 13, 2013 and Local Planning Adjustment Decision No. 3850/QD-UBND dated Jul 18, 2025, issued by the Hanoi People’s Committee.
04
Standard Form Contract
Notice of completed registration of the standard form contract No. 5711/TB-SCT dated Oct 02, 2025.
Part 2Off-plan housing information
05
Basic Design in the appraised Feasibility Study Report
Notice No. 3642/KTQLXD-QLXD4 dated Aug 28, 2025, issued by the Department of Construction Economics and Investment Management, Ministry of Construction.
06
Construction Permit
The K8CT1 project is exempt from a construction permit in accordance with prevailing laws and regulations.
07
Notice of Construction Commencement
Document No. THT-25-313 dated Oct 17, 2025.
08
Acceptance of Completed Technical Infrastructure
Acceptance Record No. THT-24-01 dated Oct 25, 2024.
09
Acceptance of Completed Foundation
Acceptance Record No. INS/K8CT1/DECV/W/Fd-001 dated Jun 30, 2026.
10
Land Use Documents
Certificate of Land Use Rights and Ownership of Assets Attached to Land No. AA 08688648 (registration No. CT2561), issued by the Hanoi People’s Committee on Sep 23, 2026; Land Allocation Decision No. 6102/QD-UBND dated Nov 25, 2024.
11
Contract for Issuance of Guarantee
Contract for Issuance of Guarantee No. SHBVN/HNB/2026/HĐCBL/THT with Shinhan Bank Vietnam Limited – Hanoi Branch and Contract for Issuance of Guarantee No. 01/2026/9763697/HDCBL with the Joint Stock Commercial Bank for Investment and Development of Vietnam (BIDV) – Cau Giay Branch, signed on Oct 23, 2026.
12
Sales Permit (eligibility for sale of off-plan housing)
Document No. 15461/SXD-QLN dated Jul 17, 2026, issued by the Department of Construction.
13
Limitations on Ownership or Use Rights; Mortgage
None. The project has not mortgaged any housing, building, floor area, land use rights or real estate project put on the market to any credit institution.
Full project and legal information
Notice to customers: THT Development only accepts payments to THT’s official bank account through authorized sales agencies. Customers are advised not to make payments to any other account.